Tool · for package buyers
Scope Estimator
Describe the halls, racks, trunks and backbone. Get the terminations, splices, test records, labels and engineer-days the package really holds, and how long it takes with the team you choose. No prices.
Estimate · no pricesGO2 Deliver
134Engineer-days
3.4Weeks with 8
7,488Test records
1,920Copper links
3,840Terminations
160MPO trunks
4,416Fibres
1,152Splices
4,328Labels
Where the days go
Copper termination48 days
Copper certification10 days
MPO trunk install20 days
Backbone splicing10 days
Fibre Tier 1 testing15 days
OTDR traces4 days
Labelling11 days
The handover pack will hold
- 1,920 copper certification results, one per link
- 4,416 fibre Tier 1 results
- 1,152 OTDR traces, both directions
- Label schedule, about 4,328 rows, to TIA-606 or your scheme
- As-built drawings, port maps and the splice-loss report
Planning figures from the assumptions above plus 15% for set-up, snagging and the pack. Access, containment readiness and change windows move them; a priced reply needs the drawings.