Handover Gap Calculator

Site tool · no sign-up

Will the cabling package certify by the date?

Put in the date the test pack is due, what is left on your cable schedule and the rates from your own daily reports. You get the shortfall, the crew that closes it and the last week you can wait. Nothing is sent anywhere unless you choose to send it.

  1. 01The date the results are due.
  2. 02What's left: links to install, links to certify.
  3. 03Your own rates from the daily report.

Your numbers stay in this browser tab. The share link holds numbers and dates only, nothing personal.

Inputs · your numbers

A · The date and your calendar

The date the results must be submitted, not practical completion.

A3Working days per week

7 ignores bank holidays.

A4Shifts per day

Two shifts means a day and a night crew.

Shutdowns, client freezes, access days.

B · What’s left on the cable schedule

Includes links installed but not yet tested.

Count links, not trunks. An MPO trunk feeding 12 duplex LC links is 12 links if each is certified.

C · The crew on site now

A team is one tester set: main and remote unit.

C3People per test team

Two is usual in a hall: one at each end.

D · Your rates, from your daily reports

Yesterday's installed count ÷ installers on the floor. Use your own figure.

Yesterday's installed count ÷ installers on the floor.

From your LinkWare saves for a full shift.

From your LinkWare saves for a full shift.

E · Supervision and start

Pick the ratio your site works to.

Earliest GO2 UK start if a complete PO pack arrived now, in working days (weekends and bank holidays not counted). The actual time is agreed in writing with each PO. Change it to test later starts.

Result

Loading the calculator…