Labelling to TIA-606: a scheme that survives handover

Identifiers for spaces, cabinets, panels and ports, and why the label, the test result and the as-built must carry the same name.

The short answer

TIA-606 gives every space, cabinet, panel, port and cable a unique identifier that can be read on site and found in the records. In practice the rule is simple: the same identifier on the label at both ends, on the test result and on the as-built drawing.

A name for everything

The standard builds identifiers from the outside in. A space (a hall or a room), a cabinet within it, usually by its floor-grid position, a panel within the cabinet, and a port on the panel.

A cable takes the identifiers of the two ports it joins. Read the label, and you know where the other end is without tracing the cable.

ElementExample identifier
Cabinet (grid position)DH2.AJ05
Panel in the cabinetDH2.AJ05-P01
Port on the panelDH2.AJ05-P01:12
Cable between two portsDH2.AJ05-P01:12 / DH2.BC11-P03:12

The format above is an example. The client's scheme decides the separators and the order; the principle does not change.

On the hall floor

  • Labels at both ends of every cable, and on every panel and port.
  • Machine-printed, durable labels, never handwritten.
  • Printed from the cable schedule, so the label cannot drift from the record.
  • Checked during the first panel check, before the rest of the hall is labelled.

One name, three places

The identifier on the label is the name of the test result and the reference on the as-built drawing. When those three agree, a client can pick any link in the hall and check it in seconds. When they do not, the whole pack has to be reconciled by hand, and handover waits.

Questions

Where should a cable label go?
At both ends, close to the termination and readable without disturbing the cable. Use durable, machine-printed labels sized for the cable.
Can we use the client's own scheme?
Yes, and usually we do. TIA-606 is the framework; the client's scheme sets the format. We confirm it before the first label is printed.
Why does labelling hold up handover?
Because results and drawings are matched to labels. If the three do not agree, the pack cannot be checked, so it cannot be accepted.

GO2DataWorks technical note, updated 18 October 2026. General guidance: your project specification and the standards it names always take precedence.